At 18:16 on October 12, 2019, the vacuum pressure of the condenser of the conventional island of Fuqing nuclear power plant, the world's first reactor of "hualong-1" undertaken by China National Nuclear fifth Corporation, reached 9.43kpa, which met the design and operation requirements, The vacuum pumping test of conventional island condenser was successfully realized! The completion of this work marks
at 18:16 on October 12, 2019, the vacuum pressure of the condenser of Fuqing nuclear power conventional island, the world's first reactor of "hualong-1" undertaken by China Nuclear fifth company, reached 9.43kpa corresponding to the condensate temperature, meeting the design and operation requirements, and the vacuum pumping test of the condenser of conventional island was successfully realized! The completion of this work marks that the cylinder hydrostatic tester Island, the world's first conventional test cylinder of "hualong-1", has fully entered the commissioning stage from the installation stage, laying the foundation for the subsequent non nuclear steam impulse
the vacuum pumping test of condenser is a large-scale comprehensive commissioning test of condenser related systems. On the basis of summarizing the construction and management experience of units 1 to 4, Fuqing nuclear power project Department of China Nuclear fifth Corporation reasonably optimized the construction management of conventional island of unit 5 and established various professional commandos, effectively ensuring the successful completion of this work. (CNNC can also refer to increase the gate size group)
LINK
Copyright © 2011 JIN SHI